Waterview Street Drainage Improvements Project

The Waterview Street Drainage Improvements Project involves replacing two storm drain systems along Waterview Street. Construction crews began work on Monday, August 16, 2021. The project is expected to take 4 weeks to complete, weather permitting. For more information on the is project, please see the Waterview Street Drainage Improvements Project fact sheet here

Project updates: 

DateActions TakenNotes to Homeowners
August 11-12Construction contractors plan to begin staging supplies and equipmentNo disturbances expected.
Please check this website for future updates
August 12Distributing the Project Fact Sheet to homeowners in the project areaPortland Public Works crew members plan to deliver the Project Fact Sheet by hand this afternoon.
August 16Construction began as scheduledConstruction workers are on-sight and handling equipment. Please drive slowly in the area.
August 20Construction is on schedule and crews
will not work over the weekend
Construction materials and equipment will remain in place. Please drive cautiously in the area.